Valutazione del sistema strutturale a pali secanti Copenhagen / Denmark / 2019

0
0 Love 196 Visits Published

During summer 2017, AVILAStudio (with Massimiliano Bellinzoni) was appointed by Andermann Engineering for the execution of a technical assessment for Claim 148&248 and FE analysis of 4 tube stations of the recently inaugurated (in summer 2019) City Ringen project in Copenhagen, in order to determine the impact of retaining walls downgrading to temporary structures. The appointment required the redesign of the tube station underground RC box under the assumption of Temporary Piles conditions and the suitability of retaining walls was assessed considering surveyed conditions, actual mechanical properties and environmental conditions.

0 users love this project
Comments
    comment
    user
    Enlarge image

    During summer 2017, AVILAStudio (with Massimiliano Bellinzoni) was appointed by Andermann Engineering for the execution of a technical assessment for Claim 148&248 and FE analysis of 4 tube stations of the recently inaugurated (in summer 2019) City Ringen project in Copenhagen, in order to determine the impact of retaining walls downgrading to temporary structures. The appointment required the redesign of the tube station underground RC box under the assumption of Temporary Piles conditions...

    Project details
    • Year 2019
    • Work started in 2017
    • Work finished in 2019
    • Main structure Reinforced concrete
    • Client Andermann Group - Avila Studio Ltd
    • Contractor We Build (Salini Impregilo)
    • Cost 10M €
    • Status Completed works
    • Type Tunnels / Underground Stations