This first phase of the works falls within a general preliminary restoration project, which involves the conversion of the building to functional multi-purpose hall auditorium, at an estimated cost of the work amounted to € 1.380.000,00.
The first batch ( € 203.521,78 of work ), or approximately 15% of the total estimated amount needed to complete the work, aimed primarily at securing the building, blocking the causes that have generated the state degradation, mainly represented by the problems related to direct or induced infiltration of rainwater, both descendants of the shell is lift from the ground through the walls. The project has defined and limited the work area to the nucleus of the church, only on ground floors and roof.
This first phase of the works falls within a general preliminary restoration project, which involves the conversion of the building to functional multi-purpose hall auditorium, at an estimated cost of the work amounted to € 1.380.000,00. The first batch ( € 203.521,78 of work ), or approximately 15% of the total estimated amount needed to complete the work, aimed primarily at securing the building, blocking the causes that have generated the state degradation, mainly represented by...
- Year 2010
- Work started in 2009
- Work finished in 2010
- Status Completed works
- Type Recovery/Restoration of Historic Buildings